ADVERSE WEATHER CONDITIONS have stopped work on City Road Lock (5) on the Regents Canal.
It was to be reopened by now, Keith Gudgin reports.
It was the gates that have been replaced that closed the lock, but the freezing weather has stopped work so that there will be a delay in getting it finished.
It was the 3rd November when the lock was closed, but is expected to reopen on Tuesday 25th November providing the weather eases.
Actons Lock
This means that the planned work on Actons Lock (7) on the Regents Canal will now start later.
With Canal & River Trust telling the plans for this lock have been adjusted to start later to allow travel through the area and onto winter moorings.
The Actons Lock closure will now begin on Friday 28th November.